| Action Date | Action Description | 
|---|---|
| Dec 22, 2023 | Maintenance Certification Request | 
| Dec 28, 2023 | Administrative Review for Completeness | 
| Jan 08, 2024 | Eng Team Review for Completeness | 
| Jan 08, 2024 | Deficient Application - Owner Notification Sent | 
| Jan 24, 2024 | Deficiency Response Received | 
| Jan 29, 2024 | Eng Team Review for Completeness | 
| Feb 05, 2024 | Application Accepted | 
| Feb 20, 2024 | HPHC Historical Preservation No Effect | 
| Mar 28, 2024 | Project Manager | 
| Mar 28, 2024 | Biologist Report | 
| Mar 28, 2024 | Engineering Report | 
| Apr 05, 2024 | Typist for Processing | 
| Apr 05, 2024 | Executive Sign Off | 
| Apr 05, 2024 | Sent to Photo Copy | 
| Apr 05, 2024 | Permit Approved | 
| Apr 09, 2024 | Permit Mailed | 
| Apr 17, 2024 | Land Evidence Date |