| Action Date | Action Description | 
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Jan 29, 2024 | Assent Application Received | 
| Feb 02, 2024 | Administrative Review for Completeness | 
| Feb 05, 2024 | Eng Team Review for Completeness | 
| Feb 05, 2024 | Application Accepted | 
| Feb 05, 2024 | Project Manager | 
| Feb 20, 2024 | HPHC Historical Preservation No Effect | 
| Mar 04, 2024 | 30 day Public Notice Issued | 
| Apr 04, 2024 | Public Notice End Date | 
| May 10, 2024 | Dock/1.1.6 Review approval | 
| Jun 25, 2024 | Engineering Report | 
| Jun 28, 2024 | Typist for Processing | 
| Jun 28, 2024 | Executive Sign Off | 
| Jun 28, 2024 | Sent to Photo Copy | 
| Jun 28, 2024 | Permit Approved | 
| Jul 03, 2024 | Permit Mailed | 
| Jul 10, 2024 | Land Evidence Date |