| Action Date | Action Description | 
|---|---|
| Jan 31, 2024 | Freshwater Wetlands Application - New - received | 
| Feb 06, 2024 | Administrative Review for Completeness | 
| Feb 23, 2024 | Eng Team Review for Completeness | 
| Feb 23, 2024 | Bio Team Review for Completeness | 
| Feb 23, 2024 | Application Accepted | 
| Feb 23, 2024 | Project Manager | 
| Mar 22, 2024 | HPHC Historical Preservation No Effect | 
| Apr 22, 2024 | Biologist Report | 
| Apr 24, 2024 | Engineering Report | 
| Apr 26, 2024 | Typist for Processing | 
| Apr 26, 2024 | Executive Sign Off | 
| Apr 26, 2024 | Sent to Photo Copy | 
| Apr 26, 2024 | Permit Approved | 
| Apr 30, 2024 | Permit Mailed | 
| May 31, 2024 | Land Evidence Date | 
| Oct 17, 2024 | Commencement of Work Notice received |