| Action Date | Action Description | 
|---|---|
| Feb 05, 2024 | Assent Application Received | 
| Feb 09, 2024 | Administrative Review for Completeness | 
| Feb 26, 2024 | Eng Team Review for Completeness | 
| Feb 26, 2024 | Application Accepted | 
| Feb 26, 2024 | Project Manager | 
| Mar 25, 2024 | 30 day Public Notice Issued | 
| Apr 25, 2024 | Public Notice End Date | 
| Apr 25, 2024 | HPHC Historical Preservation No Effect | 
| Jun 03, 2024 | Engineering Report | 
| Jun 17, 2024 | Plans Received | 
| Jun 17, 2024 | Supervisor Engineer SignOff | 
| Jun 21, 2024 | Supervisor Biologist SignOff | 
| Jun 21, 2024 | Plans Received | 
| Jun 24, 2024 | Executive Signoff of Staff Reports | 
| Jul 05, 2024 | Correspondence Received | 
| Jul 08, 2024 | Mail Agenda Notice | 
| Jul 23, 2024 | Semi-Monthly Meeting Date Scheduled | 
| Jul 31, 2024 | Council Approval Granted | 
| Jan 29, 2025 | Stipulation Package by Engineer | 
| Jan 29, 2025 | Legal Response/Decision | 
| Jan 29, 2025 | 30 Day Appeal Notification to Owner | 
| Jan 30, 2025 | Typist for Processing | 
| Jan 30, 2025 | Executive Sign Off | 
| Jan 30, 2025 | Sent to Photo Copy | 
| Jan 30, 2025 | Permit Approved | 
| Feb 27, 2025 | Permit Mailed |