| Action Date | Action Description | 
|---|---|
| Feb 22, 2024 | Assent Application Received | 
| Feb 29, 2024 | Administrative Review for Completeness | 
| Mar 05, 2024 | Eng Team Review for Completeness | 
| Mar 05, 2024 | Project Manager | 
| Mar 05, 2024 | Application Accepted | 
| Mar 18, 2024 | Engineering Report | 
| Apr 08, 2024 | Typist for Processing | 
| Apr 09, 2024 | Executive Sign Off | 
| Apr 09, 2024 | Sent to Photo Copy | 
| Apr 09, 2024 | Permit Approved | 
| Apr 09, 2024 | HPHC Historical Preservation No Effect | 
| Apr 11, 2024 | Permit Mailed | 
| Apr 30, 2024 | Duplicate Original Assent requested/mailed | 
| May 02, 2024 | Commencement of Work Notice received | 
| May 02, 2024 | Land Evidence Date |