| Action Date | Action Description | 
|---|---|
| Mar 08, 2024 | Assent Application Received | 
| Mar 15, 2024 | Administrative Review for Completeness | 
| Mar 15, 2024 | Project Manager | 
| Mar 19, 2024 | Application Accepted | 
| Mar 19, 2024 | Engineering Report | 
| Mar 20, 2024 | Typist for Processing | 
| Mar 20, 2024 | Permit Approved | 
| Mar 25, 2024 | Permit Mailed | 
| Aug 19, 2024 | Commencement of Work Notice received | 
| Aug 19, 2024 | Land Evidence Date |