| Action Date | Action Description | 
|---|---|
| HPHC Review Pending | |
| Project Manager | |
| Team Review for Completeness | |
| Mar 13, 2024 | Maintenance Certification Request | 
| Mar 20, 2024 | Administrative Review for Completeness | 
| Mar 29, 2024 | Geologist Report | 
| Apr 03, 2024 | Deficient Application - Owner Notification Sent | 
| Jun 03, 2024 | Deficiency Response Received | 
| Jun 13, 2024 | Team Review for Completeness | 
| Jun 13, 2024 | Category A assigned | 
| Jun 13, 2024 | Application Accepted | 
| Jun 13, 2024 | Project Manager | 
| Jun 25, 2024 | Plans Received | 
| Jul 16, 2024 | Geologist Report | 
| Jul 17, 2024 | Typist for Processing | 
| Jul 17, 2024 | Executive Sign Off | 
| Jul 17, 2024 | Sent to Photo Copy | 
| Jul 17, 2024 | Permit Approved | 
| Jul 18, 2024 | Permit Mailed | 
| Sep 26, 2024 | Modification Request | 
| Oct 01, 2024 | Administrative Review for Completeness | 
| Feb 28, 2025 | Correspondence Received |