| Action Date | Action Description | 
|---|---|
| Mar 20, 2024 | Assent Application Received | 
| Mar 26, 2024 | Administrative Review for Completeness | 
| Mar 29, 2024 | Eng Team Review for Completeness | 
| Mar 29, 2024 | Application Accepted | 
| Mar 29, 2024 | Project Manager | 
| Apr 05, 2024 | HPHC Historical Preservation No Effect | 
| Apr 19, 2024 | Typist for Processing | 
| Apr 19, 2024 | Executive Sign Off | 
| Apr 19, 2024 | Sent to Photo Copy | 
| Apr 19, 2024 | Permit Approved | 
| Apr 19, 2024 | Engineering Report | 
| Apr 23, 2024 | Permit Mailed |