| Action Date | Action Description | 
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Mar 25, 2024 | Assent Application Received | 
| Apr 01, 2024 | Administrative Review for Completeness | 
| Apr 02, 2024 | Bio Team Review for Completeness | 
| Apr 02, 2024 | Application Accepted | 
| Apr 02, 2024 | Project Manager | 
| Apr 02, 2024 | Category A* (Docks) | 
| Apr 09, 2024 | HPHC Historical Preservation No Effect | 
| Apr 26, 2024 | 30 day Public Notice Issued | 
| May 10, 2024 | Dock/1.1.6 Review approval | 
| May 15, 2024 | Plans Received | 
| May 26, 2024 | Public Notice End Date | 
| Jun 03, 2024 | Objections/Comments Received | 
| Jun 07, 2024 | Objections/Comments Received | 
| Jun 09, 2024 | Public Notice End Date Extension Granted | 
| Jun 13, 2024 | Objections/Comments Received | 
| Jul 12, 2024 | Public Notice End Date Extension Granted | 
| Aug 07, 2024 | Correspondence Received | 
| Sep 25, 2024 | US Army Corps of Engineers Approval Received | 
| Oct 10, 2024 | Mail Agenda Notice | 
| Oct 18, 2024 | Continued application | 
| Oct 22, 2024 | Semi-Monthly Meeting Date Scheduled | 
| Oct 29, 2024 | Biologist Report | 
| Oct 29, 2024 | Mail Agenda Notice | 
| Oct 30, 2024 | Supervisor Biologist SignOff | 
| Oct 30, 2024 | Executive Signoff of Staff Reports | 
| Oct 31, 2024 | Supervisor Engineer SignOff | 
| Nov 01, 2024 | Response to Objections received. | 
| Nov 12, 2024 | Semi-Monthly Meeting Date Scheduled | 
| Nov 12, 2024 | Council Approval Granted | 
| May 12, 2025 | Legal Response/Decision | 
| May 12, 2025 | 30 Day Appeal Notification to Owner | 
| May 13, 2025 | Typist for Processing | 
| May 13, 2025 | Executive Sign Off | 
| May 13, 2025 | Permit Approved | 
| May 16, 2025 | Permit Mailed | 
| May 27, 2025 | Land Evidence Date | 
| Jul 30, 2025 | Commencement of Work Notice received |