| Action Date | Action Description | 
|---|---|
| Assent Requirement | |
| Apr 01, 2024 | Assent Application Received | 
| Apr 01, 2024 | CHA Worksheet received | 
| Apr 04, 2024 | Administrative Review for Completeness | 
| Apr 17, 2024 | Bio Team Review for Completeness | 
| Apr 17, 2024 | Application Accepted | 
| Apr 17, 2024 | Project Manager | 
| May 13, 2024 | Plans Received | 
| May 20, 2024 | HPHC Historical Preservation No Effect | 
| Jun 05, 2024 | Additional Information Requested from Applicant | 
| Jun 18, 2024 | Plans Received | 
| Jun 24, 2024 | Biologist Report | 
| Jun 27, 2024 | Typist for Processing | 
| Jun 27, 2024 | Executive Sign Off | 
| Jun 27, 2024 | Sent to Photo Copy | 
| Jun 27, 2024 | Permit Approved | 
| Jul 03, 2024 | Permit Mailed | 
| Jul 11, 2024 | Assent Correction Mailed | 
| Jul 24, 2024 | Land Evidence Date |