| Action Date | Action Description | 
|---|---|
| May 08, 2024 | CHA Worksheet received | 
| May 08, 2024 | Assent Application Received | 
| May 14, 2024 | Administrative Review for Completeness | 
| May 14, 2024 | Bio Team Review for Completeness | 
| May 14, 2024 | Application Accepted | 
| May 14, 2024 | Project Manager | 
| Jun 17, 2024 | HPHC Historical Preservation No Effect | 
| Jul 08, 2024 | Biologist Report | 
| Jul 15, 2024 | Typist for Processing | 
| Jul 15, 2024 | Executive Sign Off | 
| Jul 15, 2024 | Sent to Photo Copy | 
| Jul 15, 2024 | Permit Approved | 
| Jul 16, 2024 | Permit Mailed | 
| Sep 05, 2024 | Duplicate Original Assent requested/mailed | 
| Sep 06, 2024 | Land Evidence Date | 
| Feb 21, 2025 | Commencement of Work Notice received |