| Action Date | Action Description | 
|---|---|
| Aug 30, 2023 | Meeting Held | 
| May 17, 2024 | CHA Worksheet received | 
| May 17, 2024 | Assent Application Received | 
| May 22, 2024 | Administrative Review for Completeness | 
| Jun 06, 2024 | Eng Team Review for Completeness | 
| Jun 06, 2024 | Bio Team Review for Completeness | 
| Jun 06, 2024 | Project Manager | 
| Jun 06, 2024 | Application Accepted | 
| Nov 26, 2024 | Note to File | 
| Dec 12, 2024 | Additional Information Requested from Applicant | 
| Jan 31, 2025 | 30 day Public Notice Issued | 
| Feb 03, 2025 | HPHC Historical Preservation No Effect | 
| Feb 05, 2025 | Correspondence Received | 
| Mar 03, 2025 | Objections/Comments Received | 
| Mar 03, 2025 | Objections/Comments Received | 
| Mar 03, 2025 | Public Notice End Date | 
| Aug 22, 2025 | Additional Information Received | 
| Oct 10, 2025 | Correspondence Received | 
| Oct 10, 2025 | Additional Information Requested from Applicant | 
| Oct 14, 2025 | Correspondence Received | 
| Oct 15, 2025 | Correspondence Mailed/Faxed/E-mailed | 
| Oct 15, 2025 | Phone Call | 
| Oct 15, 2025 | Correspondence Received | 
| Oct 16, 2025 | Correspondence Mailed/Faxed/E-mailed | 
| Oct 17, 2025 | Biologist Report | 
| Oct 17, 2025 | Engineering Report | 
| Oct 21, 2025 | Typist for Processing | 
| Oct 21, 2025 | Executive Sign Off | 
| Oct 21, 2025 | Sent to Photo Copy | 
| Oct 21, 2025 | Permit Approved | 
| Oct 21, 2025 | Permit Mailed | 
| Oct 27, 2025 | Land Evidence Date |