| Action Date | Action Description | 
|---|---|
| Jun 24, 2024 | Maintenance Certification Request | 
| Jun 28, 2024 | Administrative Review for Completeness | 
| Jul 08, 2024 | Objections/Comments Received | 
| Jul 17, 2024 | Application Accepted | 
| Jul 17, 2024 | Eng Team Review for Completeness | 
| Jul 26, 2024 | HPHC Historical Preservation No Effect | 
| Jul 30, 2024 | Objections/Comments Received | 
| May 12, 2025 | Typist for Processing | 
| May 12, 2025 | Executive Sign Off | 
| May 12, 2025 | Sent to Photo Copy | 
| May 12, 2025 | Permit Approved | 
| May 12, 2025 | Engineering Report | 
| May 16, 2025 | Permit Mailed | 
| Jun 03, 2025 | Land Evidence Date | 
| Jun 24, 2025 | Commencement of Work Notice received |