| Action Date | Action Description | 
|---|---|
| Jul 23, 2024 | CHA Worksheet received | 
| Jul 23, 2024 | Assent Application Received | 
| Jul 29, 2024 | Administrative Review for Completeness | 
| Aug 20, 2024 | Eng Team Review for Completeness | 
| Aug 20, 2024 | Deficient Application - Owner Notification Sent | 
| Nov 25, 2024 | Deficiency Response Received | 
| Dec 02, 2024 | Application Accepted | 
| Dec 09, 2024 | HPHC Historical Preservation No Effect | 
| Jan 06, 2025 | 30 day Public Notice Issued | 
| Jan 14, 2025 | Plans Received | 
| Feb 06, 2025 | Public Notice End Date | 
| Mar 24, 2025 | Plans Received | 
| Mar 24, 2025 | Engineering Report | 
| Mar 26, 2025 | Typist for Processing | 
| Mar 26, 2025 | Executive Sign Off | 
| Mar 26, 2025 | Sent to Photo Copy | 
| Mar 26, 2025 | Permit Approved | 
| Mar 28, 2025 | Permit Mailed | 
| Apr 10, 2025 | Land Evidence Date | 
| Jun 18, 2025 | Commencement of Work Notice received |