| Action Date | Action Description | 
|---|---|
| US Army Corps of Engineers Approval Required | |
| Aug 14, 2024 | Assent Application Received | 
| Aug 15, 2024 | Administrative Review for Completeness | 
| Aug 15, 2024 | Comments Received | 
| Sep 04, 2024 | Eng Team Review for Completeness | 
| Sep 04, 2024 | Application Accepted | 
| Sep 04, 2024 | Project Manager | 
| Sep 12, 2024 | 30 day Public Notice Issued | 
| Sep 13, 2024 | HPHC Historical Preservation No Effect | 
| Oct 12, 2024 | Public Notice End Date | 
| May 09, 2025 | Engineering Report | 
| May 14, 2025 | Typist for Processing | 
| Jun 09, 2025 | Executive Sign Off | 
| Jun 09, 2025 | Sent to Photo Copy | 
| Jun 09, 2025 | Permit Approved | 
| Jun 10, 2025 | Permit Mailed | 
| Jul 11, 2025 | Maintenance/Repair/Location within the Marina Perimeter | 
| Sep 26, 2025 | Note to File |