| Action Date | Action Description | 
|---|---|
| Sep 04, 2024 | Maintenance Certification Request | 
| Sep 06, 2024 | Administrative Review for Completeness | 
| Nov 14, 2024 | Plans Received | 
| Jan 08, 2025 | Application Accepted | 
| Jan 08, 2025 | Engineering Report | 
| Jan 08, 2025 | Eng Team Review for Completeness | 
| Jan 08, 2025 | Project Manager | 
| Jan 28, 2025 | HPHC Historical Preservation No Effect | 
| Jan 29, 2025 | Executive Sign Off | 
| Jan 29, 2025 | Sent to Photo Copy | 
| Jan 29, 2025 | Permit Approved | 
| Jan 29, 2025 | Typist for Processing | 
| Jan 30, 2025 | Permit Mailed | 
| May 29, 2025 | Land Evidence Date |