| Action Date | Action Description | 
|---|---|
| Sep 24, 2024 | Assent Application Received | 
| Sep 30, 2024 | Administrative Review for Completeness | 
| Oct 01, 2024 | Bio Team Review for Completeness | 
| Oct 01, 2024 | Project Manager | 
| Oct 01, 2024 | Application Accepted | 
| Oct 08, 2024 | CHA Worksheet received | 
| Oct 09, 2024 | Biologist Report | 
| Oct 22, 2024 | Typist for Processing | 
| Oct 22, 2024 | HPHC Historical Preservation No Effect | 
| Oct 22, 2024 | Executive Sign Off | 
| Oct 22, 2024 | Sent to Photo Copy | 
| Oct 22, 2024 | Permit Approved | 
| Oct 24, 2024 | Permit Mailed | 
| Oct 28, 2024 | Land Evidence Date | 
| Feb 10, 2025 | Modification Request | 
| Feb 18, 2025 | Administrative Review for Completeness | 
| Feb 18, 2025 | Bio Team Review for Completeness | 
| Feb 18, 2025 | Project Manager | 
| Feb 26, 2025 | Biologist Report | 
| Feb 28, 2025 | Typist for Processing | 
| Feb 28, 2025 | Executive Sign Off | 
| Feb 28, 2025 | Sent to Photo Copy | 
| Feb 28, 2025 | Modification Approved | 
| Feb 28, 2025 | Modification mailed | 
| Mar 05, 2025 | Permit Mailed | 
| Mar 06, 2025 | Land Evidence Date | 
| Mar 20, 2025 | HPHC Historical Preservation No Effect |