| Action Date | Action Description | 
|---|---|
| Biologist Report | |
| Engineering Report | |
| Oct 04, 2024 | CHA Worksheet received | 
| Oct 04, 2024 | Assent Application Received | 
| Oct 08, 2024 | Administrative Review for Completeness | 
| Oct 17, 2024 | Bio Team Review for Completeness | 
| Oct 17, 2024 | Application Accepted | 
| Oct 17, 2024 | Project Manager | 
| Jan 06, 2025 | HPHC Historical Preservation Comments/Concerns | 
| Jan 31, 2025 | 30 day Public Notice Issued | 
| Jan 31, 2025 | HPHC Historical Preservation Comments/Concerns | 
| Feb 05, 2025 | Correspondence Received | 
| Feb 14, 2025 | Objections/Comments Received | 
| Mar 03, 2025 | Objections/Comments Received | 
| Mar 03, 2025 | Public Notice End Date | 
| Mar 04, 2025 | Comments Received | 
| Mar 05, 2025 | Correspondence Received | 
| Oct 22, 2025 | Correspondence Mailed/Faxed/E-mailed | 
| Oct 24, 2025 | Correspondence Received | 
| Oct 29, 2025 | Additional Information Requested from Applicant |