| Action Date | Action Description | 
|---|---|
| Land Evidence Date | |
| Nov 07, 2024 | Assent Application Received | 
| Nov 12, 2024 | Administrative Review for Completeness | 
| Nov 15, 2024 | Eng Team Review for Completeness | 
| Nov 15, 2024 | Project Manager | 
| Nov 15, 2024 | Application Accepted | 
| Jan 28, 2025 | Additional Information Requested from Applicant | 
| Feb 17, 2025 | HPHC Historical Preservation No Effect | 
| Mar 19, 2025 | Additional Information Received | 
| May 01, 2025 | US Army Corps of Engineers Project Number received. | 
| Jun 09, 2025 | Biologist Report | 
| Jun 09, 2025 | Engineering Report | 
| Jun 10, 2025 | Additional Information Received | 
| Jun 16, 2025 | Public Hearing Notices Mailed | 
| Jun 16, 2025 | Mail Agenda Notice | 
| Jun 27, 2025 | Additional Information Received | 
| Jul 22, 2025 | Semi-Monthly Meeting Date Scheduled | 
| Aug 22, 2025 | Council Approval Granted | 
| Sep 11, 2025 | Legal Response/Decision | 
| Sep 24, 2025 | Stipulation Package from Biologist | 
| Sep 24, 2025 | Stipulation Package by Engineer | 
| Oct 21, 2025 | Typist for Processing | 
| Oct 21, 2025 | Executive Sign Off | 
| Oct 21, 2025 | Sent to Photo Copy | 
| Oct 21, 2025 | Permit Approved | 
| Oct 22, 2025 | Permit Mailed |