| Action Date | Action Description | 
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Nov 19, 2024 | Assent Application Received | 
| Nov 22, 2024 | Administrative Review for Completeness | 
| Nov 22, 2024 | Bio Team Review for Completeness | 
| Nov 22, 2024 | Project Manager | 
| Nov 22, 2024 | Application Accepted | 
| Dec 03, 2024 | Additional Information Received | 
| Dec 04, 2024 | Additional Information Received | 
| Dec 13, 2024 | HPHC Historical Preservation No Effect | 
| Jan 21, 2025 | 30 day Public Notice Issued | 
| Jan 29, 2025 | Dock Meeting -- Approval | 
| Feb 14, 2025 | Objections/Comments Received | 
| Feb 17, 2025 | Objections/Comments Received | 
| Feb 22, 2025 | Public Notice End Date | 
| Feb 24, 2025 | Objections/Comments Received | 
| Mar 19, 2025 | Objections/Comments Received | 
| Apr 04, 2025 | Objection withdrawal received | 
| Apr 11, 2025 | Additional Information Received | 
| Apr 21, 2025 | Objection withdrawal received | 
| Apr 30, 2025 | Dock Meeting -- Approval | 
| Apr 30, 2025 | Biologist Report | 
| May 02, 2025 | Typist for Processing | 
| May 02, 2025 | Executive Sign Off | 
| May 02, 2025 | Sent to Photo Copy | 
| May 02, 2025 | Permit Approved | 
| May 06, 2025 | Permit Mailed | 
| May 27, 2025 | Land Evidence Date | 
| Jun 09, 2025 | Commencement of Work Notice received | 
| Sep 04, 2025 | Additional Information Received | 
| Oct 02, 2025 | Additional Information Received |