| Action Date | Action Description | 
|---|---|
| Jan 30, 2025 | Assent Application Received | 
| Feb 03, 2025 | Administrative Review for Completeness | 
| Feb 26, 2025 | Bio Team Review for Completeness | 
| Feb 26, 2025 | Project Manager | 
| Feb 26, 2025 | Application Accepted | 
| Mar 17, 2025 | Additional Information Requested from Applicant | 
| Apr 29, 2025 | HPHC Historical Preservation No Effect | 
| May 02, 2025 | Additional Information Received | 
| May 14, 2025 | Biologist Report | 
| May 15, 2025 | Typist for Processing | 
| May 15, 2025 | Executive Sign Off | 
| May 15, 2025 | Sent to Photo Copy | 
| May 15, 2025 | Permit Approved | 
| May 22, 2025 | Permit Mailed | 
| Sep 23, 2025 | Land Evidence Date |