| Action Date | Action Description | 
|---|---|
| Feb 06, 2025 | Assent Application Received | 
| Feb 18, 2025 | Administrative Review for Completeness | 
| Feb 18, 2025 | Bio Team Review for Completeness | 
| Feb 21, 2025 | Application Accepted | 
| Feb 21, 2025 | Project Manager | 
| Feb 21, 2025 | Eng Team Review for Completeness | 
| Mar 21, 2025 | HPHC Historical Preservation No Effect | 
| Apr 09, 2025 | Biologist Report | 
| Apr 09, 2025 | Engineering Report | 
| Apr 14, 2025 | Typist for Processing | 
| Apr 14, 2025 | Executive Sign Off | 
| Apr 14, 2025 | Sent to Photo Copy | 
| Apr 14, 2025 | Permit Approved | 
| Apr 16, 2025 | Permit Mailed | 
| May 16, 2025 | Land Evidence Date |