| Action Date | Action Description | 
|---|---|
| Apr 14, 2025 | Assent Application Received | 
| Apr 14, 2025 | CHA Worksheet received | 
| Apr 17, 2025 | Administrative Review for Completeness | 
| Apr 23, 2025 | Additional Information Requested from Applicant | 
| May 21, 2025 | Bio Team Review for Completeness | 
| May 23, 2025 | Deficient Application - Owner Notification Sent | 
| Jul 03, 2025 | Deficiency Response Received | 
| Jul 09, 2025 | Bio Team Review for Completeness | 
| Jul 09, 2025 | Application Accepted | 
| Jul 09, 2025 | Project Manager | 
| Jul 11, 2025 | Engineering Report | 
| Jul 30, 2025 | HPHC Historical Preservation No Effect | 
| Aug 14, 2025 | Additional Information Received | 
| Aug 27, 2025 | Typist for Processing | 
| Aug 27, 2025 | Executive Sign Off | 
| Aug 27, 2025 | Sent to Photo Copy | 
| Aug 27, 2025 | Permit Approved | 
| Aug 27, 2025 | Biologist Report | 
| Aug 28, 2025 | Permit Mailed | 
| Sep 11, 2025 | Land Evidence Date | 
| Oct 14, 2025 | Commencement of Work Notice received |