| Action Date | Action Description | 
|---|---|
| Apr 17, 2025 | Assent Application Received | 
| Apr 17, 2025 | CHA Worksheet received | 
| Apr 23, 2025 | Administrative Review for Completeness | 
| May 13, 2025 | Additional Information Received | 
| May 15, 2025 | Additional Information Requested from Applicant | 
| Jun 23, 2025 | Additional Information Received | 
| Jul 02, 2025 | Correspondence Received | 
| Jul 03, 2025 | Application Accepted | 
| Jul 03, 2025 | Project Manager | 
| Jul 03, 2025 | Bio Team Review for Completeness | 
| Jul 22, 2025 | Correspondence Received | 
| Jul 24, 2025 | 15 day Public Notice Issued | 
| Aug 07, 2025 | US Army Corps of Engineers Project Number received. | 
| Aug 08, 2025 | Public Notice End Date | 
| Aug 12, 2025 | Engineering Report | 
| Aug 18, 2025 | HPHC Historical Preservation No Effect | 
| Aug 19, 2025 | Typist for Processing | 
| Aug 19, 2025 | Executive Sign Off | 
| Aug 19, 2025 | Sent to Photo Copy | 
| Aug 19, 2025 | Permit Approved | 
| Aug 21, 2025 | Permit Mailed | 
| Sep 02, 2025 | Land Evidence Date |