| Action Date | Action Description | 
|---|---|
| Apr 21, 2025 | CHA Worksheet received | 
| Apr 21, 2025 | Assent Application Received | 
| Apr 25, 2025 | Administrative Review for Completeness | 
| Apr 29, 2025 | Bio Team Review for Completeness | 
| Apr 29, 2025 | Project Manager | 
| Apr 29, 2025 | Application Accepted | 
| Jun 13, 2025 | HPHC Historical Preservation No Effect | 
| Jun 18, 2025 | Biologist Report | 
| Jun 20, 2025 | Typist for Processing | 
| Jun 20, 2025 | Executive Sign Off | 
| Jun 20, 2025 | Sent to Photo Copy | 
| Jun 20, 2025 | Permit Approved | 
| Jun 25, 2025 | Permit Mailed | 
| Jul 16, 2025 | Duplicate Original Assent requested/mailed | 
| Oct 20, 2025 | Land Evidence Date |