| Action Date | Action Description | 
|---|---|
| May 07, 2025 | Assent Application Received | 
| May 07, 2025 | Administrative Review for Completeness | 
| May 08, 2025 | Bio Team Review for Completeness | 
| May 08, 2025 | Project Manager | 
| May 08, 2025 | Application Accepted | 
| May 22, 2025 | HPHC Historical Preservation No Effect | 
| Sep 10, 2025 | Biologist Report | 
| Sep 11, 2025 | Typist for Processing | 
| Sep 11, 2025 | Executive Sign Off | 
| Sep 11, 2025 | Sent to Photo Copy | 
| Sep 11, 2025 | Permit Approved | 
| Sep 11, 2025 | Dock Post-Construction Certification by Engineer Required. | 
| Sep 16, 2025 | Permit Mailed |