| Action Date | Action Description | 
|---|---|
| Land Evidence Date | |
| Aug 07, 2025 | HPHC Historical Preservation No Effect | 
| Aug 07, 2025 | Dredge Application | 
| Aug 12, 2025 | Administrative Review for Completeness | 
| Aug 13, 2025 | Eng Team Review for Completeness | 
| Aug 13, 2025 | Project Manager | 
| Aug 13, 2025 | Application Accepted | 
| Aug 26, 2025 | Joint Public Notice | 
| Sep 02, 2025 | HPHC Historical Preservation No Effect | 
| Sep 26, 2025 | Public Notice End Date | 
| Oct 06, 2025 | Objections/Comments Received | 
| Oct 17, 2025 | Engineering Report | 
| Oct 23, 2025 | Typist for Processing | 
| Oct 23, 2025 | Executive Sign Off | 
| Oct 23, 2025 | Sent to Photo Copy | 
| Oct 23, 2025 | Permit Approved | 
| Oct 28, 2025 | Permit Mailed |