| Action Date | Action Description |
|---|---|
| Jul 11, 2005 | Assent Application Received |
| Jul 12, 2005 | Administrative Review for Completeness |
| Jul 19, 2005 | Team Review for Completeness |
| Jul 19, 2005 | Application Accepted |
| Jul 19, 2005 | Category B assigned |
| Aug 01, 2005 | HPHC Review Pending |
| Aug 01, 2005 | Joint Public Notice |
| Aug 12, 2005 | HPHC Historical Preservation No Effect |
| Sep 12, 2005 | Correspondence Received |
| Sep 13, 2005 | Biologist Report |
| Sep 15, 2005 | Correspondence Received |
| Sep 15, 2005 | Correspondence Received |
| Sep 19, 2005 | Additional Information Received |
| Sep 22, 2005 | Correspondence Received |
| Sep 23, 2005 | Engineering Report |
| Sep 23, 2005 | Dredge Report |
| Sep 26, 2005 | Executive Sign Off |
| Oct 01, 2005 | Public Notice End Date |
| Oct 05, 2005 | Ready to Schedule Semi-Monthly Meeting |
| Oct 05, 2005 | Mail Agenda Notice |
| Oct 11, 2005 | Continued Application by the Council |
| Oct 11, 2005 | Semi-Monthly Meeting Date Scheduled |
| Oct 19, 2005 | Mail Agenda Notice |
| Oct 25, 2005 | Semi-Monthly Meeting Held |
| Oct 25, 2005 | Council Approval Granted |
| Oct 25, 2005 | Semi-Monthly Meeting Date Scheduled |
| Oct 25, 2005 | DEM Dredge Permit |
| Nov 14, 2005 | Stipulation Package from Biologist |
| Nov 14, 2005 | Stipulation Package by Engineer |
| Nov 14, 2005 | Typist for Processing |
| Nov 14, 2005 | Executive Sign Off |
| Nov 14, 2005 | Sent to Photo Copy |
| Nov 14, 2005 | Permit Approved |
| Nov 22, 2005 | Land Evidence Date |
| Nov 29, 2005 | Legal Response/Decision |
| Dec 02, 2005 | Under Review/Decision |