| Action Date | Action Description |
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Nov 16, 2020 | Assent Application Received |
| Nov 18, 2020 | Administrative Review for Completeness |
| Nov 25, 2020 | Category A* (Docks) |
| Dec 23, 2020 | Application Accepted |
| Dec 23, 2020 | Project Manager |
| Dec 23, 2020 | Bio Team Review for Completeness |
| Dec 29, 2020 | Category A* (Docks) |
| Feb 05, 2021 | HPHC Historical Preservation No Effect |
| Feb 05, 2021 | HPHC Review Pending |
| Sep 09, 2021 | 30 day Public Notice Issued |
| Oct 09, 2021 | Public Notice End Date |
| Oct 14, 2021 | Dock/1.1.6 Review approval |
| Jan 20, 2022 | Biologist Report |
| Jan 26, 2022 | Permit Approved |
| Jan 26, 2022 | Typist for Processing |
| Jan 26, 2022 | Executive Sign Off |
| Jan 26, 2022 | Sent to Photo Copy |
| Feb 01, 2022 | Permit Mailed |
| Feb 18, 2022 | Land Evidence Date |