| Action Date | Action Description |
|---|---|
| Nov 06, 2023 | CHA Worksheet received |
| Nov 06, 2023 | Assent Application Received |
| Nov 09, 2023 | Administrative Review for Completeness |
| Nov 14, 2023 | Bio Team Review for Completeness |
| Nov 14, 2023 | Project Manager |
| Nov 14, 2023 | Application Accepted |
| Dec 20, 2023 | HPHC Historical Preservation No Effect |
| Feb 05, 2024 | Additional Information Requested from Applicant |
| Mar 07, 2024 | Correspondence Received |
| Mar 15, 2024 | Additional Information Received |
| Mar 15, 2024 | CHA Worksheet received |
| May 08, 2024 | Biologist Report |
| May 20, 2024 | Typist for Processing |
| May 20, 2024 | Executive Sign Off |
| May 20, 2024 | Sent to Photo Copy |
| May 20, 2024 | Permit Approved |
| May 21, 2024 | Permit Mailed |
| May 24, 2024 | Land Evidence Date |
| May 28, 2024 | Commencement of Work Notice received |
| Jun 20, 2024 | Additional Information Received |
| Jun 20, 2024 | Assent Requirement |