| Action Date | Action Description |
|---|---|
| Nov 14, 2023 | CHA Worksheet received |
| Nov 14, 2023 | Assent Application Received |
| Nov 16, 2023 | Administrative Review for Completeness |
| Nov 22, 2023 | Bio Team Review for Completeness |
| Nov 22, 2023 | Project Manager |
| Nov 22, 2023 | Application Accepted |
| Jan 03, 2024 | HPHC Historical Preservation No Effect |
| Jan 04, 2024 | Additional Information Requested from Applicant |
| Feb 02, 2024 | Additional Information Received |
| Mar 14, 2024 | Additional Information Requested from Applicant |
| Apr 10, 2024 | Plans Received |
| Apr 10, 2024 | CHA Worksheet received |
| Apr 19, 2024 | Biologist Report |
| Apr 22, 2024 | Typist for Processing |
| Apr 22, 2024 | Executive Sign Off |
| Apr 22, 2024 | Sent to Photo Copy |
| Apr 22, 2024 | Permit Approved |
| Apr 23, 2024 | Permit Mailed |
| May 15, 2024 | Land Evidence Date |