| Action Date | Action Description |
|---|---|
| Violation Exists on this Site (NOV) | |
| Sep 06, 2005 | Assent Application Received |
| Sep 07, 2005 | Administrative Review for Completeness |
| Sep 07, 2005 | Team Review for Completeness |
| Sep 07, 2005 | Application Accepted |
| Sep 07, 2005 | Category A* (Docks) |
| Sep 08, 2005 | 30 day Public Notice Issued |
| Sep 30, 2005 | HPHC Review Pending |
| Oct 17, 2005 | US Army Corp of Engineers Permit Date |
| Oct 19, 2005 | US Army Corps of Engineers Approval Received |
| Oct 24, 2005 | Biologist Report |
| Oct 28, 2005 | Engineering Report |
| Oct 31, 2005 | Typist for Processing |
| Oct 31, 2005 | Executive Sign Off |
| Oct 31, 2005 | Sent to Photo Copy |
| Nov 17, 2005 | Objections/Comments Received |
| Nov 18, 2005 | Correspondence Received |
| Nov 21, 2005 | Public Notice End Date |
| Nov 21, 2005 | Correspondence Received |
| Dec 07, 2005 | Ready to Schedule Semi-Monthly Meeting |
| Dec 07, 2005 | Mail Agenda Notice |
| Dec 13, 2005 | Semi-Monthly Meeting Date Scheduled |
| Dec 19, 2005 | Correspondence Received |
| Jan 03, 2006 | Mail Agenda Notice |
| Jan 10, 2006 | Semi-Monthly Meeting Held |
| Jan 10, 2006 | Council Approval Granted |
| Jan 10, 2006 | Semi-Monthly Meeting Date Scheduled |
| Jan 20, 2006 | Legal Response/Decision |
| Apr 13, 2006 | Stipulation Package from Biologist |
| Apr 13, 2006 | Stipulation Package by Engineer |
| Jun 07, 2006 | Correspondence Mailed/Faxed/E-mailed |
| Jul 06, 2006 | Objections/Comments Received |
| Mar 06, 2007 | Ready to Schedule Semi-Monthly Meeting |
| Mar 07, 2007 | Management Review |
| Mar 16, 2007 | Mail Agenda Notice |
| Apr 04, 2007 | Continuance Requested by Applicant |
| Apr 10, 2007 | Continuance request by applicant granted by Director |
| Apr 10, 2007 | Semi-Monthly Meeting Date Scheduled |
| Apr 12, 2007 | Mail Agenda Notice |
| Apr 24, 2007 | Semi-Monthly Meeting Date Scheduled |
| Oct 29, 2007 | Ready to Schedule Semi-Monthly Meeting |
| Oct 29, 2007 | Mail Agenda Notice |
| Nov 13, 2007 | Continued Application by the Council |
| Nov 13, 2007 | Semi-Monthly Meeting Date Scheduled |
| Nov 27, 2007 | Continuance Requested by Applicant |
| Jan 22, 2008 | Semi-Monthly Meeting Date Scheduled |
| Feb 20, 2008 | Additional Information Received |
| Feb 29, 2008 | Typist for Processing |
| Feb 29, 2008 | Executive Sign Off |
| Feb 29, 2008 | Sent to Photo Copy |
| Feb 29, 2008 | Permit Approved |
| Mar 24, 2008 | Land Evidence Date |