| Action Date | Action Description |
|---|---|
| Sep 10, 2013 | Assent Application Received |
| Sep 10, 2013 | Administrative Review for Completeness |
| Oct 01, 2013 | Team Review for Completeness |
| Oct 01, 2013 | Application Accepted |
| Oct 01, 2013 | Correspondence Received |
| Oct 01, 2013 | 30 day Public Notice Issued |
| Nov 01, 2013 | Public Notice End Date |
| Nov 29, 2013 | US Army Corps of Engineers Approval Received |
| Dec 17, 2013 | Policy Review |
| Dec 31, 2013 | Typist for Processing |
| Dec 31, 2013 | Executive Sign Off |
| Dec 31, 2013 | Sent to Photo Copy |
| Dec 31, 2013 | Permit Approved |
| Jan 28, 2014 | Assent Correction Request Received |
| Jan 29, 2014 | Assent Correction Mailed |