| Action Date | Action Description |
|---|---|
| Sep 30, 2013 | Assent Application Received |
| Oct 01, 2013 | Administrative Review for Completeness |
| Dec 03, 2013 | HPHC Historical Preservation No Effect |
| Dec 13, 2013 | Team Review for Completeness |
| Dec 13, 2013 | Application Accepted |
| Jul 11, 2014 | 30 day Public Notice Issued |
| Aug 11, 2014 | Public Notice End Date |
| Aug 21, 2014 | Engineering Report |
| Sep 03, 2014 | Permit Approved |
| Sep 03, 2014 | Typist for Processing |
| Sep 04, 2014 | Executive Sign Off |
| Sep 04, 2014 | Sent to Photo Copy |
| Jan 14, 2015 | Land Evidence Date |