| Action Date | Action Description |
|---|---|
| Jul 28, 2014 | Assent Application Received |
| Jul 29, 2014 | Administrative Review for Completeness |
| Jul 29, 2014 | Team Review for Completeness |
| Jul 29, 2014 | Application Accepted |
| Jul 31, 2014 | Biologist Report |
| Aug 04, 2014 | Typist for Processing |
| Aug 04, 2014 | Permit Approved |
| Aug 05, 2014 | Executive Sign Off |
| Aug 05, 2014 | Sent to Photo Copy |
| Aug 08, 2014 | Land Evidence Date |
| Sep 04, 2014 | HPHC Historical Preservation No Effect |
| Dec 11, 2014 | Commencement of Work Notice received |