| Action Date | Action Description |
|---|---|
| Apr 17, 2015 | Assent Application Received |
| Apr 17, 2015 | Administrative Review for Completeness |
| Apr 21, 2015 | Team Review for Completeness |
| Apr 21, 2015 | Application Accepted |
| May 21, 2015 | HPHC Historical Preservation No Effect |
| Aug 27, 2015 | Plans Received |
| Aug 28, 2015 | 30 day Public Notice Issued |
| Sep 11, 2015 | Plans Received |
| Oct 08, 2015 | Engineering Report |
| Oct 13, 2015 | Additional Information Received |
| Oct 22, 2015 | Biologist Report |
| Oct 27, 2015 | Council Approval Granted |
| Oct 27, 2015 | Stipulation Package from Biologist |
| Oct 27, 2015 | Stipulation Package by Engineer |
| Nov 17, 2015 | Typist for Processing |
| Nov 18, 2015 | Executive Sign Off |
| Nov 18, 2015 | Sent to Photo Copy |
| Nov 18, 2015 | Permit Approved |
| Nov 27, 2015 | Land Evidence Date |
| Mar 01, 2016 | Legal Response/Decision |
| Mar 31, 2016 | Modification Request |
| Apr 01, 2016 | Administrative Review for Completeness |
| Apr 04, 2016 | Team Review for Completeness |
| Apr 04, 2016 | Team Review for Completeness |
| Apr 04, 2016 | Biologist Report |
| Apr 04, 2016 | Engineering Report |
| Apr 05, 2016 | Typist for Processing |
| Apr 05, 2016 | Executive Sign Off |
| Apr 05, 2016 | Sent to Photo Copy |
| Apr 05, 2016 | Modification Approved |
| Apr 13, 2016 | HPHC Historical Preservation No Effect |
| Apr 13, 2016 | Land Evidence Date |
| Jul 17, 2017 | Correspondence Received |
| Mar 26, 2018 | Modification Request |
| Mar 27, 2018 | Administrative Review for Completeness |
| Mar 27, 2018 | Entry of Appearance Received |
| Mar 30, 2018 | Team Review for Completeness |
| Apr 05, 2018 | Deficient Application - Owner Notification Sent |
| Jan 11, 2019 | Deficient Application Discarded/No deficiency Reponse |