| Action Date | Action Description |
|---|---|
| May 20, 2015 | Assent Application Received |
| May 27, 2015 | Administrative Review for Completeness |
| Jun 02, 2015 | Team Review for Completeness |
| Jun 03, 2015 | Application Accepted |
| Jun 03, 2015 | Category B assigned |
| Jun 12, 2015 | HPHC Historical Preservation No Effect |
| Aug 18, 2015 | Correspondence Mailed/Faxed/E-mailed |
| Aug 19, 2016 | 30 day Public Notice Issued |
| Sep 19, 2016 | Public Notice End Date |
| Sep 23, 2016 | Public Notice End Date Extension Granted |
| Sep 23, 2016 | Public Notice End Date |
| Oct 25, 2016 | Biologist Report |
| Oct 25, 2016 | Engineering Report |
| Oct 25, 2016 | Executive Signoff of Staff Reports |
| Nov 09, 2016 | Ready to Schedule Semi-Monthly Meeting |
| Nov 09, 2016 | Mail Agenda Notice |
| Nov 21, 2016 | Mail Agenda Notice |
| Nov 22, 2016 | Semi-Monthly Meeting Postponed |
| Nov 22, 2016 | Semi-Monthly Meeting Date Scheduled |
| Nov 29, 2016 | Semi-Monthly Meeting Date Scheduled |
| Nov 29, 2016 | Council Approval Granted |
| Dec 01, 2016 | Legal Response/Decision |
| Dec 01, 2016 | 30 Day Appeal Notification to Owner |
| Dec 15, 2016 | Stipulation Package from Biologist |
| Dec 15, 2016 | Stipulation Package by Engineer |
| Jan 03, 2017 | Typist for Processing |
| Jan 03, 2017 | Executive Sign Off |
| Jan 03, 2017 | Sent to Photo Copy |
| Jan 03, 2017 | Permit Approved |
| Jan 25, 2017 | Land Evidence Date |
| Apr 06, 2017 | Correspondence Received |
| Jun 05, 2018 | Correspondence Received |