| Action Date | Action Description |
|---|---|
| Jul 08, 2015 | Aquaculture Application Received |
| Jul 13, 2015 | Aquaculture Administrative Review |
| Jul 13, 2015 | Application Accepted |
| Jul 15, 2015 | 30 day Public Notice Issued |
| Jul 27, 2015 | HPHC Historical Preservation No Effect |
| Aug 11, 2015 | Objections/Comments Received |
| Aug 15, 2015 | Public Notice End Date |
| Oct 07, 2015 | Aquaculture correspondence received |
| Oct 08, 2015 | Objections/Comments Received |
| Oct 15, 2015 | US Army Corps of Engineers Approval Received |
| Dec 31, 2015 | Category B assigned |
| Feb 05, 2016 | Objections/Comments Received |
| Feb 11, 2016 | 30 day Public Notice Issued |
| Feb 18, 2016 | Objections/Comments Received |
| Feb 29, 2016 | Objections/Comments Received |
| Mar 14, 2016 | Public Notice End Date |
| Mar 29, 2016 | US Army Corps of Engineers Approval Received |
| May 06, 2016 | Aquaculture Report |
| May 10, 2016 | Executive Signoff of Staff Reports |
| May 16, 2016 | Ready to Schedule Semi-Monthly Meeting |
| May 16, 2016 | Mail Agenda Notice |
| May 24, 2016 | Council Approval Granted |
| May 24, 2016 | Semi-Monthly Meeting Date Scheduled |
| Jun 06, 2016 | Legal Response/Decision |
| Jun 06, 2016 | 30 Day Appeal Notification to Owner |
| Jun 07, 2016 | Stipulation Package from Aquaculture Coordinator |
| Jun 09, 2016 | Typist for Processing |
| Jun 13, 2016 | Executive Sign Off |
| Jun 13, 2016 | Sent to Photo Copy |
| Jun 13, 2016 | Aquaculture Lease Mailed |
| Jun 13, 2016 | Permit Approved |
| Nov 02, 2016 | Aquaculture Lease Received |
| Nov 02, 2016 | Aquaculture Lease Payment |
| Nov 10, 2016 | Aquaculture Bond Received |
| Nov 21, 2016 | Aquaculture Lease Payment |
| Oct 24, 2017 | Aquaculture Lease Cover Letter sent |
| Nov 27, 2017 | Aquaculture Lease Payment |
| Nov 27, 2017 | Aquaculture Yearly Questionnaire |
| Dec 03, 2018 | Aquaculture Lease Cover Letter sent |
| Dec 31, 2018 | Aquaculture Lease Payment |
| Jan 24, 2019 | Aquaculture Yearly Questionnaire |
| Dec 10, 2019 | Aquaculture Lease Cover Letter sent |
| Jan 09, 2020 | Aquaculture Yearly Questionnaire |
| Jan 09, 2020 | Aquaculture Lease Payment |
| Jan 09, 2020 | Aquaculture Bond Received |
| Dec 21, 2020 | Aquaculture Lease Cover Letter sent |
| Dec 24, 2020 | Aquaculture Lease Payment |
| Mar 16, 2021 | Aquaculture Yearly Questionnaire |
| Dec 28, 2021 | Aquaculture Lease Cover Letter sent |
| Dec 31, 2021 | Aquaculture Bond Received |
| Mar 14, 2022 | Aquaculture Yearly Questionnaire |
| Mar 14, 2022 | Aquaculture Lease Payment |
| Nov 07, 2024 | Aquaculture Bond Expiration |