| Action Date | Action Description |
|---|---|
| Aug 20, 2015 | Assent Application Received |
| Aug 26, 2015 | Administrative Review for Completeness |
| Sep 18, 2015 | Team Review for Completeness |
| Sep 18, 2015 | Team Review for Completeness |
| Sep 18, 2015 | Application Accepted |
| Sep 29, 2015 | HPHC Historical Preservation No Effect |
| Oct 20, 2015 | Biologist Report |
| Oct 20, 2015 | Engineering Report |
| Oct 21, 2015 | Typist for Processing |
| Oct 22, 2015 | Executive Sign Off |
| Oct 22, 2015 | Sent to Photo Copy |
| Oct 22, 2015 | Permit Approved |
| Nov 16, 2015 | Land Evidence Date |
| Jun 11, 2019 | Extension of Permit Request |
| Jul 17, 2019 | Extension Approved |
| May 04, 2020 | Modification Request |
| May 05, 2020 | Administrative Review for Completeness |
| May 07, 2020 | Correspondence Mailed/Faxed/E-mailed |
| May 18, 2020 | Extension of Permit Request |
| May 20, 2020 | Bio Team Review for Completeness |
| May 20, 2020 | Project Manager |
| Jun 04, 2020 | Process Extension |
| Jun 04, 2020 | Enforcement Compliance Inspection Required |
| Jun 05, 2020 | Biologist Report |
| Jun 05, 2020 | Typist for Processing |
| Jun 05, 2020 | Extension Approved |
| Jun 05, 2020 | Modification Approved |
| Jun 11, 2020 | HPHC Historical Preservation No Effect |
| Jun 11, 2020 | HPHC Review Pending |
| Sep 05, 2020 | Land Evidence Date |