| Action Date | Action Description |
|---|---|
| Oct 19, 2018 | Assent Application Received |
| Oct 22, 2018 | Administrative Review for Completeness |
| Oct 23, 2018 | Team Review for Completeness |
| Oct 23, 2018 | Application Accepted |
| Nov 07, 2018 | HPHC Historical Preservation No Effect |
| Nov 28, 2018 | Additional Information Requested from Applicant |
| Jan 04, 2019 | 30-Day Notification of Cancellation letter |
| Jan 18, 2019 | Additional Information Received |
| Jan 30, 2019 | Additional Information Requested from Applicant |
| Mar 07, 2019 | Additional Information Received |
| Mar 14, 2019 | Biologist Report |
| Mar 14, 2019 | Additional Information Received |
| Mar 18, 2019 | Typist for Processing |
| Mar 18, 2019 | Executive Sign Off |
| Mar 18, 2019 | Sent to Photo Copy |
| Mar 18, 2019 | Permit Approved |
| Jun 18, 2019 | Phone Call |