| Action Date | Action Description |
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Jul 23, 2019 | Assent Application Received |
| Jul 24, 2019 | Administrative Review for Completeness |
| Jul 26, 2019 | Team Review for Completeness |
| Jul 26, 2019 | Application Accepted |
| Jul 26, 2019 | Category B assigned |
| Aug 05, 2019 | 30 day Public Notice Issued |
| Aug 22, 2019 | HPHC Review Pending |
| Aug 22, 2019 | HPHC Historical Preservation No Effect |
| Sep 05, 2019 | Public Notice End Date |
| Dec 11, 2019 | Additional Information Received |
| Jan 21, 2020 | US Army Corps of Engineers Approval Received |
| Jan 27, 2020 | Executive Signoff of Staff Reports |
| Jan 27, 2020 | Engineering Report |
| Feb 12, 2020 | Ready to Schedule Semi-Monthly Meeting |
| Feb 12, 2020 | Mail Agenda Notice |
| Feb 25, 2020 | Council Approval Granted |
| Feb 25, 2020 | Semi-Monthly Meeting Date Scheduled |
| Mar 04, 2020 | Stipulation Package by Engineer |
| Mar 04, 2020 | Legal Response/Decision |
| Mar 09, 2020 | Typist for Processing |
| Mar 09, 2020 | Executive Sign Off |
| Mar 09, 2020 | Sent to Photo Copy |
| Mar 09, 2020 | Permit Approved |
| Aug 14, 2020 | Duplicate Original Assent requested/mailed |
| Aug 24, 2020 | Land Evidence Date |