| Action Date | Action Description |
|---|---|
| Administrative Review for Completeness | |
| HPHC Historical Preservation No Effect | |
| Jun 04, 2013 | Assent Application Received |
| Jun 05, 2013 | Administrative Review for Completeness |
| Jul 19, 2013 | Team Review for Completeness |
| Jul 19, 2013 | Team Review for Completeness |
| Jul 19, 2013 | Additional Information Received |
| Jul 23, 2013 | Application Accepted |
| Jul 23, 2013 | Biologist Report |
| Jul 23, 2013 | Plans Received |
| Jul 23, 2013 | 30 day Public Notice Issued |
| Aug 14, 2013 | HPHC Historical Preservation No Effect |
| Aug 23, 2013 | Public Notice End Date |
| Sep 25, 2013 | Plans Received |
| Sep 27, 2013 | Additional Information Received |
| Oct 09, 2013 | Public Hearing Notices Mailed |
| Oct 18, 2013 | Stipulation Package from Biologist |
| Nov 12, 2013 | Council Approval Granted |
| Nov 12, 2013 | Semi-Monthly Meeting Date Scheduled |
| Nov 12, 2013 | Public Hearing Scheduled |
| Nov 12, 2013 | Semi-Monthly Meeting Held |
| Nov 19, 2013 | 30 Day Appeal Notification to Owner |
| Nov 19, 2013 | Legal Response/Decision |
| Nov 21, 2013 | US Army Corps of Engineers Approval Received |
| Dec 04, 2013 | Typist for Processing |
| Dec 04, 2013 | Permit Approved |
| Dec 05, 2013 | Executive Sign Off |
| Dec 05, 2013 | Sent to Photo Copy |
| Dec 09, 2013 | Land Evidence Date |
| Mar 14, 2016 | Modification Request |