| Action Date | Action Description |
|---|---|
| Jul 19, 2019 | Assent Application Received |
| Jul 22, 2019 | Administrative Review for Completeness |
| Jul 23, 2019 | Team Review for Completeness |
| Jul 23, 2019 | Application Accepted |
| Jul 23, 2019 | Category A* (Docks) |
| Jul 30, 2019 | HPHC Historical Preservation No Effect |
| Jul 30, 2019 | HPHC Review Pending |
| Sep 23, 2019 | 30 day Public Notice Issued |
| Oct 23, 2019 | Public Notice End Date |
| Oct 23, 2019 | Comments Received |
| Nov 19, 2019 | Phone Call |
| Jan 03, 2020 | Meeting Held |
| Feb 25, 2020 | Additional Information Requested from Applicant |
| Apr 22, 2020 | Additional Information Received |
| Jun 16, 2020 | Typist for Processing |
| Jun 16, 2020 | Executive Sign Off |
| Jun 16, 2020 | Sent to Photo Copy |
| Jun 16, 2020 | Permit Approved |
| Jun 16, 2020 | Biologist Report |
| Jun 16, 2020 | Engineering Report |
| Aug 11, 2020 | Land Evidence Date |
| Oct 07, 2025 | Note to File |