| Action Date | Action Description |
|---|---|
| Aug 18, 2020 | Assent Application Received |
| Aug 18, 2020 | Administrative Review for Completeness |
| Aug 25, 2020 | Eng Team Review for Completeness |
| Aug 25, 2020 | Bio Team Review for Completeness |
| Aug 31, 2020 | Project Manager |
| Aug 31, 2020 | Application Accepted |
| Sep 16, 2020 | Joint Public Notice |
| Sep 22, 2020 | HPHC Review Pending |
| Sep 22, 2020 | HPHC Historical Preservation No Effect |
| Oct 17, 2020 | Public Notice End Date |
| Oct 20, 2020 | Water Quality Certification |
| Dec 04, 2020 | Additional Information Requested from Applicant |
| Dec 18, 2020 | Additional Information Received |
| Jan 15, 2021 | US Army Corps of Engineers Approval Received |
| May 17, 2021 | Stipulation Package by Engineer |
| May 17, 2021 | Stipulation Package from Biologist |
| May 17, 2021 | Biologist Report |
| May 17, 2021 | Engineering Report |
| May 19, 2021 | Typist for Processing |
| May 25, 2021 | Executive Sign Off |
| May 25, 2021 | Sent to Photo Copy |
| May 25, 2021 | Permit Approved |
| Aug 19, 2021 | Land Evidence Date |