| Action Date | Action Description |
|---|---|
| Aug 25, 2021 | Assent Application Received |
| Aug 31, 2021 | Administrative Review for Completeness |
| Aug 31, 2021 | CHA Worksheet received |
| Sep 03, 2021 | Bio Team Review for Completeness |
| Sep 03, 2021 | Application Accepted |
| Sep 03, 2021 | Project Manager |
| Oct 26, 2021 | HPHC Review Pending |
| Oct 26, 2021 | HPHC Historical Preservation No Effect |
| Nov 15, 2021 | Additional Information Requested from Applicant |
| Dec 13, 2021 | Plans Received |
| Dec 30, 2021 | Plans Received |
| Jan 10, 2022 | Plans Received |
| Jan 11, 2022 | Biologist Report |
| Jan 12, 2022 | Typist for Processing |
| Jan 12, 2022 | Permit Approved |
| Jan 18, 2022 | Permit Mailed |
| Jan 25, 2022 | Land Evidence Date |
| Sep 27, 2022 | Note to File |
| Oct 06, 2022 | Assent Requirement |