| Action Date | Action Description |
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Biologist Report | |
| Apr 28, 2021 | Assent Application Received |
| May 03, 2021 | Administrative Review for Completeness |
| May 04, 2021 | Bio Team Review for Completeness |
| May 04, 2021 | Application Accepted |
| May 04, 2021 | Project Manager |
| May 07, 2021 | Additional Information Requested from Applicant |
| May 17, 2021 | HPHC Historical Preservation No Effect |
| May 17, 2021 | HPHC Review Pending |
| May 20, 2021 | Additional Information Requested from Applicant |
| Jun 01, 2021 | Correspondence Received |
| Jun 03, 2021 | Correspondence Mailed/Faxed/E-mailed |
| Jun 08, 2021 | Plans Received |
| Jun 14, 2021 | 30 day Public Notice Issued |
| Jul 14, 2021 | Public Notice End Date |
| Aug 25, 2021 | Stipulation Package from Biologist |
| Aug 25, 2021 | Typist for Processing |
| Aug 25, 2021 | Executive Sign Off |
| Aug 25, 2021 | Sent to Photo Copy |
| Aug 25, 2021 | Permit Approved |
| Aug 25, 2021 | Biologist Report |
| Aug 31, 2021 | Permit Mailed |
| Sep 08, 2021 | Land Evidence Date |
| May 16, 2025 | Modification Request |
| May 23, 2025 | Administrative Review for Completeness |
| Jun 05, 2025 | Bio Team Review for Completeness |
| Jun 05, 2025 | Project Manager |
| Jun 05, 2025 | Application Accepted |
| Jun 24, 2025 | HPHC Historical Preservation No Effect |
| Aug 19, 2025 | 30 day Public Notice Issued |
| Aug 20, 2025 | US Army Corps of Engineers Project Number received. |
| Sep 19, 2025 | Public Notice End Date |