Application 2025-11-023 Details

Back to List


Actions:

Action Date Action Description
HPHC Review Pending
Biologist Report
Engineering Report
Nov 07, 2025 Assent Application Received
Nov 07, 2025 Administrative Review for Completeness
Nov 07, 2025 CHA Worksheet received
Nov 13, 2025 Application Accepted
Nov 13, 2025 Eng Team Review for Completeness
Nov 13, 2025 Bio Team Review for Completeness
Nov 13, 2025 Project Manager

Details:

File No
2025-11-023
Town
Providence
First Name
Department of Transportation
Last Name
Street
I-195 Washington Bridge (Westb
Location
I-195 Washington Bridge (Westbound)
Plat/Map
Lot/Block
Decision Date
Dock Reg.No
Project
Replace demolished bridge (#700) westbound and Gano St. off-ramp
Description
Roadways, Bridges, Pk Lots, Rr Line (Pri
Water Area
Easement
0
Acceptance Date
Nov 13, 2025