| Action Date | Action Description |
|---|---|
| Land Evidence Date | |
| Dock Post-Construction Certification by Engineer Required. | |
| Mar 04, 2025 | Assent Application Received |
| Mar 07, 2025 | Administrative Review for Completeness |
| Mar 12, 2025 | Bio Team Review for Completeness |
| Mar 19, 2025 | Correspondence Mailed/Faxed/E-mailed |
| Mar 19, 2025 | Eng Team Review for Completeness |
| Mar 19, 2025 | Application Accepted |
| Mar 19, 2025 | Project Manager |
| Apr 18, 2025 | Correspondence Received |
| Apr 29, 2025 | HPHC Historical Preservation No Effect |
| Jul 28, 2025 | Additional Information Received |
| Aug 06, 2025 | 30 day Public Notice Issued |
| Aug 07, 2025 | US Army Corps of Engineers Project Number received. |
| Sep 06, 2025 | Public Notice End Date |
| Oct 28, 2025 | Additional Information Received |
| Nov 28, 2025 | Engineering Report |
| Dec 01, 2025 | Typist for Processing |
| Dec 01, 2025 | Executive Sign Off |
| Dec 01, 2025 | Sent to Photo Copy |
| Dec 01, 2025 | Permit Approved |
| Dec 02, 2025 | Permit Mailed |