| Action Date | Action Description |
|---|---|
| Land Evidence Date | |
| Dock Post-Construction Certification by Engineer Required. | |
| Sep 04, 2025 | Assent Application Received |
| Sep 10, 2025 | Administrative Review for Completeness |
| Sep 11, 2025 | Bio Team Review for Completeness |
| Sep 11, 2025 | Project Manager |
| Sep 11, 2025 | Application Accepted |
| Oct 10, 2025 | HPHC Historical Preservation No Effect |
| Oct 24, 2025 | 30 day Public Notice Issued |
| Oct 28, 2025 | US Army Corps of Engineers Project Number received. |
| Nov 23, 2025 | Public Notice End Date |
| Dec 04, 2025 | Typist for Processing |
| Dec 04, 2025 | Executive Sign Off |
| Dec 04, 2025 | Sent to Photo Copy |
| Dec 04, 2025 | Permit Approved |
| Dec 04, 2025 | Biologist Report |
| Dec 08, 2025 | Permit Mailed |