| Action Date | Action Description |
|---|---|
| Land Evidence Date | |
| Dock Post-Construction Certification by Engineer Required. | |
| Jun 30, 2025 | Assent Application Received |
| Jul 08, 2025 | Administrative Review for Completeness |
| Jul 16, 2025 | Eng Team Review for Completeness |
| Jul 16, 2025 | Project Manager |
| Jul 16, 2025 | Application Accepted |
| Jul 25, 2025 | HPHC Historical Preservation No Effect |
| Sep 09, 2025 | 30 day Public Notice Issued |
| Oct 09, 2025 | Public Notice End Date |
| Nov 05, 2025 | Dock/1.1.6 Review approval |
| Nov 13, 2025 | Plans Received |
| Dec 15, 2025 | Engineering Report |
| Dec 18, 2025 | Typist for Processing |
| Dec 18, 2025 | Executive Sign Off |
| Dec 18, 2025 | Sent to Photo Copy |
| Dec 18, 2025 | Permit Approved |
| Dec 22, 2025 | Permit Mailed |